The Realistic Range, and Why It Varies So Much

"How long will it take" is one of the hardest questions to answer honestly, because a full house renovation can mean very different things. Here's the realistic range based on property size and scope:

PropertyScopeRealistic timeline
3-bedroom terrace Full strip-out and refit — kitchen, bathroom, electrics, plumbing, plastering, decorating 3–4 months
4–5 bedroom house Full renovation including an extension or loft conversion 5–7 months

These are on-site build timelines once work starts. If your project includes an extension or loft conversion that needs full planning permission rather than Permitted Development, add a further 8–10 weeks for the council's determination period before any building work can begin.

The Phase-by-Phase Breakdown

Every full house renovation, regardless of size, moves through the same broad phases. Here's what happens in each one and roughly how it fits into the overall programme:

Phase 1

Design, Survey & Planning

Structural surveys, drawings, structural engineer calculations where needed, and planning or Building Regulations applications submitted. Your fixed-price quote is itemised to every trade before any work starts on site. If planning permission is required, this phase alone can take 8–10 weeks while the council determines the application.

Phase 2

Strip-Out

Old kitchens, bathrooms, flooring and fittings removed; skips ordered; the property stripped back to a clean shell ready for first fix. Usually the fastest phase, typically 3–5 days for a full property.

Phase 3

Structural Work & First Fix

Any wall removal, steel beam installation, extension groundworks or loft structural work happens here, alongside first-fix electrics and plumbing — the cabling and pipework that goes in before walls are closed up. This is usually the longest single phase, particularly where structural or extension work is involved.

Phase 4

Plastering

Walls and ceilings skimmed once first fix is signed off. Plaster needs to dry fully before second fix can begin, which is a hard time constraint that can't be rushed without affecting the finish.

Phase 5

Second Fix

Kitchen units, bathroom suites, flooring, sockets, switches, radiators and doors all go in. This is when the property starts to visibly look finished, even though several weeks of work usually remain.

Phase 6

Decorating & Snagging

Final painting, tiling grout and sealant, fitting handles and trims, and a full snagging walkthrough before handover. We address any snagging items before you move back in, not after.

Why First Fix and Plastering Take the Longest

Of all six phases, first fix and plastering combined usually account for the largest share of the programme. Every other trade depends on them being finished correctly, you can't tile a bathroom before the plastering is dry, and you can't fit a kitchen before the electrics are first-fixed. Rushing this stage to hit an artificial deadline is the single biggest cause of renovation problems we see in properties we're asked to fix after another contractor's work.

How Individual Trades Add Up

A full house renovation typically bundles several trades that, individually, have their own timelines. Seeing them separately helps explain why a full property takes longer than the sum of any one room:

In a full house renovation these trades run in a coordinated sequence rather than back-to-back, which is why an experienced project manager, not just skilled tradespeople, is what actually keeps a multi-trade renovation on schedule.

Do You Need to Move Out?

In most cases, yes. For a full property renovation you'll typically need alternative living arrangements for the duration, particularly once electrics, water and heating are disconnected during first fix. We plan the programme as tightly as possible to minimise the period you're out, and the property is secured at the end of every working day.

What Can Extend the Timeline

A good contractor flags any of these immediately with a revised, costed timeline, not silence followed by a missed deadline. We provide a week-by-week programme before work starts and update it transparently if anything changes. See our full house renovation service page for more on how we manage multi-trade projects, or browse completed renovations on our projects page.